ALTERNATIVES

In Fall 2023, the Project Team started the process to identify and evaluate the alternatives that best meet the project’s Purpose and Need and Project Goals. 

Alternatives Evaluation Process
Before identifying alternatives, the Project Team drafted a framework to evaluate alternatives. Evaluation criteria were developed based on the Purpose and Need and Project Goals.  The team met with the Project Advisory Committee (PAC) and Technical Team (TT) to discuss the framework—revising the process and criteria based on comments received.

The evaluation process involves these major steps (see Figure 1):

  • Develop Range of Alternatives (core concepts and supplemental elements)
  • Level 1 Screening
  • Level 2 Screening
  • Identify Recommended Alternative

Figure 1. Alternatives Process Flowchart 

Alternatives Process Flowchart

These steps are further discussed below.

RANGE OF ALTERNATIVES

To help identify alternatives, the project corridor was divided into three segments reflecting different land use and traffic characteristics (see Figure 2).

Figure 2. Project Segments

project-segments-2

The Project Team identified improvement alternatives by reviewing planning documents and getting input from the TT, PAC, and the public during the February 2024 public meetings. 

Alternatives were categorized as either core concepts or supplemental elements. Core concepts consist of WY 22 lane configuration and new transportation connections intended to meet the Purpose and Need.  Supplemental elements include intersection and other improvements that do not meet the Purpose and Need individually but can improve or supplement the core concepts in meeting the project needs.

Core concepts evaluated in Level 1 include:

Core concepts evaluated in Level 1 include

For a complete list of alternatives including supplemental elements, refer to the public meeting #2 exhibits and handout materials found here.

LEVEL 1 SCREENING

In Level 1, the core concepts were evaluated against the criteria at a high level to determine if they meet the Purpose and Need or have a fatal flaw.  Alternatives that did not meet the Purpose and Need, or for which a fatal flaw is identified, were eliminated from further consideration. Alternatives which met the Purpose and Need were retained for Level 2 screening.

Not all core concepts were evaluated for each of the three segments.  The Project team identified which alternatives to evaluate in each of the three project segments based on traffic and safety characteristics, as well as PAC input.

Segment 1: Evaluation Results

Seven mainline alternatives and two transportation linkage alternatives were evaluated in Level 1, including the No Action Alternative.  Three were eliminated from further consideration:

2-Lane Low Build – this alternative was eliminated because it fails to: reduce peak period travel time delay, accommodate forecasted person trips, and improve reliable access for emergency vehicles.

Peak Period Shoulder (PPS) –eliminated because of the potential to increase crashes at intersections, failure to improve intersection operations, and failure to support travel mode choice.

3-Lane –eliminated because it fails to reduce peak period travel time delay and accommodate future forecasted person trips.

The Segment 1 alternatives that met all the screening criteria and carried forward to Level 2 analysis include:

  • 4-Lane Add General Purpose
  • 4-Lane Add Managed Lane
  • 5-Lane
  • Transportation Linkage – Extend Tribal Trail Road to WY 22

The No Action Alternative did not meet the Purpose and Need but was carried forward to Level 2 as a baseline condition for comparison.

Segment 2

Four mainline alternatives, including the No Action, were evaluated in Level 1. Only the Peak Period Shoulder alternative was eliminated because of the potential to increase crashes at intersections, failure to improve intersection operations, and failure to support travel mode choice. Alternatives that met all the screening criteria and advanced to Level 2 include:

  • 2-Lane Low Build
  • 3-Lane

The No Action Alternative did not meet the Purpose and Need but was carried forward to Level 2 as a baseline condition for comparison.

Segment 3

Three mainline alternatives, including the No Action, were evaluated.  The Peak Period Shoulder was eliminated for the same reasons mentioned above.  The Segment 3 alternatives that met all the screening criteria and were therefore carried forward to Level 2 analysis include:

  • No Action
  • 3-Lane Low Build

IDENTIFY THE RECOMMENDED ALTERNATIVE

After completing Level 2 screening, the remaining core concept(s) will be combined with the highest performing supplemental elements to form a Recommended Alternative.